Tampa Electric crews are raising critical equipment at the First Street Substation in Ruskin to protect it from future flooding.

The utility announced the work Oct. 28 in a post on X, citing lessons learned from Hurricane Helene's storm surge. "Hurricane Helene showed us how powerful storm surge can be," the company said. "We're putting those lessons to work."

Tampa Electric has not disclosed a timeline or specified which equipment is being elevated. The company said the project will strengthen grid reliability for the area served by the Ruskin substation.